# Estimate

## Phase 1: Understand the Task

從參數讀取任務描述。如果描述太模糊,沒辦法做有意義的估算,先請對方釐清再繼續。

讀 CLAUDE.md 取得專案脈絡:技術堆疊、coding standard、架構模式,還有任何估算準則。

如果任務跟某個有文件的功能或系統有關,就讀 `design/gdd/` 裡相關的設計文件。要按章節讀:用 Grep 工具(pattern `^#`,content mode)找出你需要的標題,再用 offset 和 limit 讀那幾段範圍。

---

## Phase 2: Scan Affected Code

找出需要改動的檔案和模組:

- 用 Grep 對每個受影響的檔案量測大小和分支數 — 這個 skill 只有 Read、Glob 和 Grep
  三個工具,所以這些計數就是量測:
  - **Size:** `Grep pattern="[^[:space:]]" path="[file]" output_mode="count"` —
    非空白行數。
  - **Branching:** `Grep pattern="(^|[^A-Za-z0-9_])(if|elif|for|foreach|while|match|switch|case|catch)([^A-Za-z0-9_]|$)|&&|[|][|]" path="[file]" output_mode="count"` —
    含有分支或布林運算子的行數。這個計數
    只是 cyclomatic complexity 的近似值(註解和字串也會被算進去);要講成近似值,
    絕對不要講成實測的複雜度。
  - **Dependencies:** 每個檔案引入了什麼 — `preload`/`load(`(GDScript)、
    `using`(C#)、`#include`(C++)— 以及還有哪些檔案參照它。
  - Grep 算不出來的檔案(不存在、二進位、讀不了),要在 Notes
    and Assumptions 底下點名,不要直接從總數裡漏掉。
- 找出跟其他系統的整合點
- 檢查受影響區域現有的測試覆蓋
- 從 `production/sprints/` 讀過去的 sprint 資料,找類似的已完成任務和歷史 velocity。
  **如果沒有**,要在 Notes and Assumptions 底下講明 — 「No sprint history found;
  this estimate is not calibrated to the team's velocity」— 並且把它當成信心等級裡的風險,
  不要默默把數字加大來墊。

---

## Phase 3: Analyze Complexity Factors

**Code Complexity:**
- 受影響檔案的大小和分支數(Phase 2 的 Grep 計數)
- 相依項目的數量和耦合程度
- 這是動到 core/engine 程式碼,還是 leaf/feature 程式碼
- 能不能沿用現有模式,還是需要新模式

**Scope:**
- 動到的系統數量
- 新增程式碼 vs 修改現有程式碼
- 需要新增多少測試覆蓋
- 需不需要資料遷移或設定變更

**Risk:**
- 新技術或不熟的函式庫
- 需求不清楚或有歧義
- 依賴還沒完成的工作
- 跨系統整合的複雜度
- 對效能敏感

---

## Phase 4: Generate the Estimate

```markdown
## Task Estimate: [Task Name]
Generated: [Date]

### Task Description
[Restate the task clearly in 1-2 sentences]

### Complexity Assessment

| Factor | Assessment | Notes |
|--------|-----------|-------|
| Systems affected | [List] | [Core, gameplay, UI, etc.] |
| Files likely modified | [Count] | [Key files listed below] |
| Size of affected files | [N non-blank lines; M branch lines] | Grep counts; branch lines approximate complexity |
| New code vs modification | [Ratio] | |
| Integration points | [Count] | [Which systems interact] |
| Test coverage needed | [Low / Medium / High] | |
| Existing patterns available | [Yes / Partial / No] | |

**Key files likely affected:**
- `[path/to/file1]` -- [what changes here]

### Effort Estimate

| Scenario | Days | Assumption |
|----------|------|------------|
| Optimistic | [X] | Everything goes right, no surprises |
| Expected | [Y] | Normal pace, minor issues, one round of review |
| Pessimistic | [Z] | Significant unknowns surface, blocked for a day |

**Recommended budget: [Y days]**

### Confidence: [High / Medium / Low]

[Explain which factors drive the confidence level for this specific task.]

### Risk Factors

| Risk | Likelihood | Impact | Mitigation |
|------|-----------|--------|------------|

### Dependencies

| Dependency | Status | Impact if Delayed |
|-----------|--------|-------------------|

### Suggested Breakdown

| # | Sub-task | Estimate | Notes |
|---|----------|----------|-------|
| 1 | [Research / spike] | [X days] | |
| 2 | [Core implementation] | [X days] | |
| 3 | [Testing and validation] | [X days] | |
| | **Total** | **[Y days]** | |

### Notes and Assumptions
- [Key assumption that affects the estimate]
- [Any caveats about scope boundaries]
```

輸出估算時附一段簡短摘要:建議預算、信心等級,以及最大的單一風險因素。

這個 skill 是唯讀的 — 不會寫任何檔案。Verdict: **COMPLETE** — estimate generated.

---

## Phase 5: Next Steps

- 信心等級是 Low:建議在承諾之前先做一個限時的 spike(`/prototype`)。
- 任務超過 10 天:建議用 `/create-stories` 拆成比較小的 story。
- 要排進行程:跑 `/sprint-plan update`,把它加進下一個 sprint(如果專案沒有 sprint plan,像預設的 minimal workflow,就改加進 brief 的 build order)。

### Guidelines

- 一律給範圍(optimistic / expected / pessimistic),絕對不要只給單一數字
- 建議預算要用 expected 的估算,不要用 optimistic 的
- 四捨五入到半天為單位 — 超過一天的任務用小時來估,會給人錯誤的精確感
- 不要默默加估算的水分 — 把風險明講出來,讓團隊自己決定
- 只要做法還沒決定,或核心需求還是 TBD,信心就是 Low — 建立在還沒做的決定上的範圍,就是用猜的

英文原文

---
name: estimate
description: "Estimate task effort from complexity, dependencies, velocity, risk. Structured estimate with confidence levels."
argument-hint: "[task-description]"
user-invocable: true
allowed-tools: Read, Glob, Grep
model: sonnet
---

# Estimate

## Phase 1: Understand the Task

Read the task description from the argument. If the description is too vague to estimate meaningfully, ask for clarification before proceeding.

Read CLAUDE.md for project context: tech stack, coding standards, architectural patterns, and any estimation guidelines.

Read relevant design documents from `design/gdd/` if the task relates to a documented feature or system. Read them by section: find the headings you need with the Grep tool (pattern `^#`, content mode) and Read those ranges with offset and limit.

---

## Phase 2: Scan Affected Code

Identify files and modules that would need to change:

- Measure size and branching with Grep, per affected file — Read, Glob and Grep
  are this skill's only tools, so these counts are the measurement:
  - **Size:** `Grep pattern="[^[:space:]]" path="[file]" output_mode="count"` —
    non-blank lines.
  - **Branching:** `Grep pattern="(^|[^A-Za-z0-9_])(if|elif|for|foreach|while|match|switch|case|catch)([^A-Za-z0-9_]|$)|&&|[|][|]" path="[file]" output_mode="count"` —
    lines holding a branch or a boolean operator. The count
    approximates cyclomatic complexity (comments and strings count too); report
    it as that, never as a measured complexity.
  - **Dependencies:** what each file pulls in — `preload`/`load(` (GDScript),
    `using` (C#), `#include` (C++) — and which other files reference it.
  - Name any file Grep could not count (missing, binary, unreadable) under Notes
    and Assumptions rather than leaving it out of the totals.
- Identify integration points with other systems
- Check for existing test coverage in the affected areas
- Read past sprint data from `production/sprints/` for similar completed tasks and historical velocity.
  **If there is none**, say so under Notes and Assumptions — "No sprint history found;
  this estimate is not calibrated to the team's velocity" — and treat that as a risk
  in the confidence level, not as a silent padding of the figures.

---

## Phase 3: Analyze Complexity Factors

**Code Complexity:**
- Size and branching of the affected files (Phase 2's Grep counts)
- Number of dependencies and coupling level
- Whether this touches core/engine code vs leaf/feature code
- Whether existing patterns can be followed or new patterns are needed

**Scope:**
- Number of systems touched
- New code vs modification of existing code
- Amount of new test coverage required
- Data migration or configuration changes needed

**Risk:**
- New technology or unfamiliar libraries
- Unclear or ambiguous requirements
- Dependencies on unfinished work
- Cross-system integration complexity
- Performance sensitivity

---

## Phase 4: Generate the Estimate

```markdown
## Task Estimate: [Task Name]
Generated: [Date]

### Task Description
[Restate the task clearly in 1-2 sentences]

### Complexity Assessment

| Factor | Assessment | Notes |
|--------|-----------|-------|
| Systems affected | [List] | [Core, gameplay, UI, etc.] |
| Files likely modified | [Count] | [Key files listed below] |
| Size of affected files | [N non-blank lines; M branch lines] | Grep counts; branch lines approximate complexity |
| New code vs modification | [Ratio] | |
| Integration points | [Count] | [Which systems interact] |
| Test coverage needed | [Low / Medium / High] | |
| Existing patterns available | [Yes / Partial / No] | |

**Key files likely affected:**
- `[path/to/file1]` -- [what changes here]

### Effort Estimate

| Scenario | Days | Assumption |
|----------|------|------------|
| Optimistic | [X] | Everything goes right, no surprises |
| Expected | [Y] | Normal pace, minor issues, one round of review |
| Pessimistic | [Z] | Significant unknowns surface, blocked for a day |

**Recommended budget: [Y days]**

### Confidence: [High / Medium / Low]

[Explain which factors drive the confidence level for this specific task.]

### Risk Factors

| Risk | Likelihood | Impact | Mitigation |
|------|-----------|--------|------------|

### Dependencies

| Dependency | Status | Impact if Delayed |
|-----------|--------|-------------------|

### Suggested Breakdown

| # | Sub-task | Estimate | Notes |
|---|----------|----------|-------|
| 1 | [Research / spike] | [X days] | |
| 2 | [Core implementation] | [X days] | |
| 3 | [Testing and validation] | [X days] | |
| | **Total** | **[Y days]** | |

### Notes and Assumptions
- [Key assumption that affects the estimate]
- [Any caveats about scope boundaries]
```

Output the estimate with a brief summary: recommended budget, confidence level, and the single biggest risk factor.

This skill is read-only — no files are written. Verdict: **COMPLETE** — estimate generated.

---

## Phase 5: Next Steps

- If confidence is Low: recommend a time-boxed spike (`/prototype`) before committing.
- If the task is > 10 days: recommend breaking it into smaller stories via `/create-stories`.
- To schedule the task: run `/sprint-plan update` to add it to the next sprint (if the project has no sprint plan, as on the default minimal workflow, add it to the brief's build order instead).

### Guidelines

- Always give a range (optimistic / expected / pessimistic), never a single number
- The recommended budget should be the expected estimate, not the optimistic one
- Round to half-day increments — estimating in hours implies false precision for tasks longer than a day
- Do not pad estimates silently — call out risk explicitly so the team can decide
- Confidence is Low whenever the approach is undecided or the core requirements are still TBD — a range built on an unmade decision is a guess